One of my favorite definitions of “hacking” is the creative reuse of tools for new and unexpected purposes. Hacking is using your email account as a hard drive, using your bicycle seat to open a beer, using Minecraft’s red bricks to create a calculator in the game.
The opposite of hacking is marketing. Marketing tells you that this particular non-stick pan is the pan you’ll use to make omelettes, and you’ll do it in the morning dressed in fashionable clothing in a nice kitchen. It includes a photo and inspirational copywriting to drive this home. Marketing dictates a style, context, and purpose for even the most general-purpose products. This narrative needs to be specific so that you can readily imagine it: it’s you, in an Airbnb, laughing with friends.
Technology is seeing a little return to complexity. Dreamweaver gave way to hand-coding websites, which is now leading into Webflow, which is a lot like Dreamweaver. Evernote give way to minimal Markdown notes, which are now becoming Notion, Coda, or Craft. Visual Studio was “disrupted” by Sublime Text and TextMate, which are now getting replaced by Visual Studio Code. JIRA was replaced by GitHub issues, which is getting outmoded by Linear. The pendulum swings back and forth, which isn’t a bad thing
The Scrum process says to break down stories into tasks to make estimation easier, encourage collaboration and to be able to show more granular progress during a sprint.
But after a few sprints, we decided to do the next sprint without creating tasks. As a result we drastically increased our velocity and never went back. Here I'll jot down some of the reasons we decided to do this:
Breaking down stories into tasks is time consuming
The tasks we came up with invariably would change as we worked on the stories
Tasks are repetitive
Tasks were often carried out in parallel
Our estimates didn't improve
It decluttered our task board
It encouraged collaboration throughout the sprint
While we started our process by following Scrum to the letter, we soon realised that breaking down stories into tasks was something that wasn’t worthwhile for us. In the end we realised that it was overplanning and poor use of our time. In the end we used that time to get on with the work and deliver at a significantly faster pace.