politics
The spatial dimension of democracy
Political chains of influence
What kind of world it's going to be
Bridges as walls
We infantilize ourselves
Thoughts On Shitpost Diplomacy
Behold! I have an opinion. An EXCLUSIVE opinion.
An Article by Heather BurnsPart of the joy of working in digital policy in the UK is that many of your days start like this:
I, a Tory politician, have a brilliant plan / erudite commentary / a policy announcement on tech policy strategy. Click here to read it in this EXCLUSIVE Elite Broadsheet Newspaper piece.
We all know full well that this is how the game of politics works. These brilliant plans, erudite commentaries, and policy announcements aren’t made for you plebs. They’re made for the machine to feed the beast inside it.
The way we usually do infrastructure
A Fragment by Noah SmithThe bipartisan deal contains a pot of money to repair America’s roads and bridges, and build a few more besides. This is the way we usually do infrastructure in America. First we build a ton of roads and bridges that are highly expensive to maintain, especially with our ruinously high construction costs (see this recent article by Jerusalem Demsas). Then, because costs are so high, we wait for a long time to repair the roads and bridges, until civil engineers start screeching, roads get potholed, and there’s a bridge collapse or two. Then we muster up the political will to throw the requisite shit-ton of money at the problem, the potholes and weak bridges get repaired for twice the amount it would have cost had we done it on a regular schedule and three times the amount it would cost if we were a normal rich country. And the whole cycle begins again.
Software that nobody wants
Finding value is the result of enabling individual and group-level discovery attempts. It's not the result of everyone following one leader's gut.
What just happened is a new software product/feature was created that no customer wanted. This happens way too often. In fact, most hyper important software projects that must be done by date certain or else, have deep flaws that cause some variation of this phenomenon, flaws that include:
- Not wanted - Company specified a solution to a problem that customers don't actually have
- No Rarity - Company is pursuing an iKnockoff of existing products. The market already has two scaled competitors with working solutions, customers naturally spend budget on products that are already successful to avoid risk
- Incorrect Packaging - Customers need a website, but the company created an iOS app instead
- Incorrect Pricing - Customers need SaaS pricing, but the company created a shrink wrapped, on-premise solution with CapEx and maintenance agreements instead
The 'date scrum' anti-pattern
Date Scrum is an R&D pattern where developers are asked to estimate software project requirements upfront for the entirety of the project. After the project is green lighted and the budget is set based on the final estimates, the team then holds daily scrums to status and manage risk as they “iterate” the solution toward the release date. To some, this approach is described as doing Waterfall in sprints.
The fundamental problem with Date Scrum is that the team is de-focused from discovering the best solution. Instead they are heavily focused on delivering Something™ by the Date™. Engineers are problem solvers, and if the primary problem becomes delivering Something™ that will pass QA by the Date™, they will, with enough pressure, solve that exact problem.