"Rappers" on the roof of the electrostatic precipitator knock the accumulated dust free, letting it fall into the storage hopper. Each rapper is the size and shape of a baseball bat. Inside is an electromagnet that pulls a steel plunger upward, then allows it to fall again, producing a sharp knock. The rappers are energized at seemingly random intervals, producing a haunting, syncopated music. (The rhythm seemed more modern jazz than rap.)
Today population forecasts are based on extensive and reliable data. However, no such demographic base exists for the world's growing population of machines and devices. Now may be the time to take machine demography seriously and enter into real discussions about machine population control.
The couple of years in question here saw one of the largest bureaucracies anywhere undergo a convulsion in which it tried to reconceive itself as a non- or even anti-bureaucracy, which at first might sound like nothing more than an amusing bit of bureaucratic folly. In fact, it was frightening; it was a little like watching an enormous machine come to consciousness and start trying to think and feel like a real human.
The Scrum process says to break down stories into tasks to make estimation easier, encourage collaboration and to be able to show more granular progress during a sprint.
But after a few sprints, we decided to do the next sprint without creating tasks. As a result we drastically increased our velocity and never went back. Here I'll jot down some of the reasons we decided to do this:
Breaking down stories into tasks is time consuming
The tasks we came up with invariably would change as we worked on the stories
Tasks are repetitive
Tasks were often carried out in parallel
Our estimates didn't improve
It decluttered our task board
It encouraged collaboration throughout the sprint
While we started our process by following Scrum to the letter, we soon realised that breaking down stories into tasks was something that wasn’t worthwhile for us. In the end we realised that it was overplanning and poor use of our time. In the end we used that time to get on with the work and deliver at a significantly faster pace.