The [Lake Erie] ecosystem underwent a series of changes, each of which were related. There was an increase in the human population; which led to higher phosophorus levels in the water; which led, at last, to an increased level of algae in the lake. In effect, Lake Erie’s ecosystem was rewritten. Changed by human activities into…something else.
But Franklin cites the study because it’s doing something slightly novel: applying Selye’s principle of stress to ecological systems, suggesting that they are, much like humans, just as susceptible to external stressors. And I’ve been thinking about that a lot lately, especially this week. Because Franklin’s suggesting that the work begins not by “fixing the system.” Rather, she suggests it’s about shifting the priority a little: to removing whatever stress you can.
In the early days, design systems promised us more consistent interfaces, more collaborative teams, and improved shipping times. While they’ve certainly delivered on some of those fronts, they’ve introduced new challenges too. Let’s talk through what’s working well—and what could be working better—as we take a closer look at the systems between us and our work.
The Scrum process says to break down stories into tasks to make estimation easier, encourage collaboration and to be able to show more granular progress during a sprint.
But after a few sprints, we decided to do the next sprint without creating tasks. As a result we drastically increased our velocity and never went back. Here I'll jot down some of the reasons we decided to do this:
Breaking down stories into tasks is time consuming
The tasks we came up with invariably would change as we worked on the stories
Tasks are repetitive
Tasks were often carried out in parallel
Our estimates didn't improve
It decluttered our task board
It encouraged collaboration throughout the sprint
While we started our process by following Scrum to the letter, we soon realised that breaking down stories into tasks was something that wasn’t worthwhile for us. In the end we realised that it was overplanning and poor use of our time. In the end we used that time to get on with the work and deliver at a significantly faster pace.